An occupancy certificate confirms a finished building matches its sanctioned plan and is fit to occupy. In Hyderabad it unlocks the 10% of built up area mortgaged to the authority, it is needed for most home loans and resale, and under the CURE Act officials who connect utilities to buildings without an OC now face disciplinary action. Verify it on the approving authority's record before you pay.
What an OC certifies
When a building is complete, the owner or builder files a completion notice with the authority that sanctioned it. After inspection, the authority issues an occupancy certificate stating that the structure was built as per the sanctioned plan and the building rules, with permitted deviations only. The sanction conditions of most Hyderabad buildings state plainly that the OC is compulsory before anyone occupies the building.
| Document | Issued when | Proves |
|---|---|---|
| Building permission and sanctioned plan | Before construction | What may be built: floors, setbacks, built up area |
| Occupancy certificate | After completion and inspection | What was built matches what was allowed |
Why it matters more in 2026
The Core Urban Region (Integrated Governance) Act, 2026, which replaced the GHMC Act, 1955 for the Greater Hyderabad, Cyberabad and Malkajgiri corporations from October 2026, tightened OC enforcement. Reports on its notification say an official who provides electricity, water or other services to a building without an OC can face disciplinary action, including removal from service. For buyers, that means a flat in a building without an OC may struggle to get permanent connections, on top of the long standing problems with home loans and resale.
Where to verify it
Do not accept a photocopy alone. Check the record of the authority that sanctioned the building:
- BuildNow Telangana is the state's current portal for building permissions, layout approvals and occupancy certificates in GHMC, HMDA and DTCP areas. It replaced TG bPASS from December 2025.
- TG bPASS, GHMC and HMDA records hold permissions and OCs issued earlier. Sanctions issued under the old system remain valid.
- The TG RERA project page often carries the completion or occupancy documents uploaded by the promoter. See our TG RERA verification guide.
Match the permit number, the survey or plot number, the number of floors and the tower names on the OC against the sanctioned plan and your sale documents.
The 10% mortgaged area
For most buildings above the smallest category, the builder mortgages 10% of the built up area to the sanctioning authority as security that the building will follow the plan. The mortgage is released only when the OC is issued. Sanction conditions also typically say the mortgaged area may be registered only after the OC is produced. If you are buying a flat that sits within the mortgaged portion of a building that never received an OC, you inherit that problem.
Check the mortgage deed. Ask which flats were mortgaged to GHMC or HMDA. A 30 year encumbrance certificate will usually show the registered mortgage in favour of the authority and, if released, the release.
Partial OCs and multi tower projects
Large gated communities often receive OCs tower by tower, or for some floors first. A partial OC for Towers A to C says nothing about Tower D. Ask for the OC that names your tower, and if the clubhouse or amenities are still under construction, ask how the builder will complete them and on what date.
Buildings that do not need one
Small individual residential buildings are exempt. Under the BuildNow rules, an individual residential building on a plot up to 200 square metres with a height up to 7 metres does not need to apply for an OC, and no mortgage is taken for that category. Apartments and anything larger need an OC. If a seller claims an exemption for an apartment block, treat it as a red flag.
What to ask the seller
- The building permission number and sanctioned plan.
- The OC naming your tower, with its number and date.
- Release of the 10% mortgage, if the building was in that category.
- For deviations noticed on site, whether they were regularised.
- Permanent electricity and water connection references in the building's name.
Our documents checklist for buyers covers the rest of the file.
Frequently asked questions
Is an occupancy certificate mandatory for apartments in Hyderabad?
Yes. Sanction conditions require an OC before a building is occupied, and only small individual houses on plots up to 200 square metres and 7 metres in height are exempt from applying.
Where can I check an OC online in Telangana?
Check the record of the sanctioning authority. BuildNow Telangana handles permissions and OCs for GHMC, HMDA and DTCP areas since December 2025, while earlier records sit with TG bPASS, GHMC or HMDA.
What is the 10% mortgaged area?
Builders mortgage 10% of the built up area to the sanctioning authority as security for following the plan. It is released when the OC is issued, and sanction conditions usually bar registering those units until then.
Can I get a home loan without an OC?
Many lenders will not fund a ready flat without an OC, and sanction conditions direct lenders to fund only the permitted built up area. Ask your lender before you commit.
What changed under the CURE Act in 2026?
Reports on the Act's notification in October 2026 say officials who connect electricity, water or other services to a building without an OC can face disciplinary action, making the OC far more important for occupation.
Official sources checked
- BuildNow Telangana, building permissions and occupancy certificates
- Greater Hyderabad Municipal Corporation
- Hyderabad Metropolitan Development Authority, occupancy certificate procedure
- TG RERA project records
This guide is general information for property owners and is not legal, tax or financial advice. Rules change, and your facts matter. Confirm your specific situation with a Chartered Accountant or a Telangana advocate before acting.
Not sure the building has a valid OC?
We verify the sanction, OC, mortgage release and title before you sign.